Neka Combined Cycle
Status of Project: Completed
Project Highlights
Role of Parhoon Tarh: EPC Contractor as member of Parhoon Tarh-Ameran Ofogh-Niroo Tavan J.V.
Client: MAPNA Group
Consultant Engineer: Monenco Consulting Engineers
Location: Iran-Mazandaran Province
Project Cost: 11 million USD
Project Duration: 31 months
Featured Images
Project Volumes
Excavation: 60,000 m3
Concrete Volume: 15,000 m3
Formwork: 16,000 m2
Reinforcement: 2,500 tons
Steel Works: 2,500 tons
Sandwich Panel: 10,000 m2
Project Specification
Capacity: 160 MW
Number of Units: 2 units
Capacity of Each Unit: 80 MW
Project Goals
- Power generation & improving environmental conditions