Industrial Buildings and Site Construction of Negin Mahestan Petrochemical Company

Industrial Buildings and Site Construction of Negin Mahestan Petrochemical Company

Negin Mahestan Kangan Petrochemical Company is located in approximately 20 Km southeast Kangan City in Tonbak Region, Boushher Province, between Cement Plant and phase 12 of Gas Field Development Plan of South pars Special Economic Zone, Kangan Petrochemical Complex. The project of Negin Mahestan Petrochemical Company includes supplying the necessary materials, and executing the civil development, site and access road buildings, construction of the foundation and concrete structures, industrial buildings consisting of three packaging building, extrusion, co-catalyst, and, electrical –electronic, and safety facilities related to it, subsurface piping system; and earthing system in both the heavy and linear light polyethylene production units.

Status of Project: In Progress

Project Highlights

Role of Parhoon Tarh: Contractor of Construction Operations and Site Building
Client: Negin Mahestan Kangan Petrochemical Company
Consultant Engineer: Sazehpardazi Iran Consultant Engineers
Location: Boushehr- Kangan
Project Cost: 2,570 billion IRR
Project Duration: 24 months

 

Project images

Project Volumes

Concrete work: 30,000  m3
Excavation: 95,000  m3
Formwork: 62,000  m2
Reinforcement: 3,600 tons
Steel structures: 200 tons
Embankment: 6,500  m3
Subsurface piping system: 29,000 m

Project Specification

Number of industrial buildings: Three buildings consisting of packing building, extrusion, co-catalyst and electrical facilities
Extrusion building: 2800  m2
Extrusion substation building: 650  m2
Additive storage and control room buildings: 400  m2
C-catalyst building: 260  m2
Packaging building: 3500  m2
 

Project Goals

  • Construction of industrial buildings, access roads, site building, underground/subsurface piping sytem….in the area of Negin Mahestan Petrochemical Company
post

Construction and civil operations of Setareh Sabz-e Siraf Refinery

Construction and civil operations of Setareh Sabz-e Siraf Refinery

Industrial buildings and civil engineering of Setareh Sabz-e Siraf Refinery Civil and construction operations of Setareh Sabz-e Siraf Refinery in Areas one and two, located in Asalouyeh of South Pars field, declared to this company through tender by Setareh Sabz-e Siraf Refinery Company in December 2020.


Current status of the project: Under construction

Key information of the project

Role of Parhoon Tarh: Main contractor
Employer: Setareh Sabz-e Siraf Refinery Company
Consultant: Nargan Consultant Engineers Company
Location: Hormozgan Province
Value of the project: 4,260 billion Rials
Length of the projects: 12 months

 

Project images

Volumes of the projects:

Excavation: 600,000  m3
Embankment: 300,000  m3
Armature: 9000 tons
Concrete pouring: 80,000  m3
Concrete molds: 300,000  m2
Fence: 160 tons
Stone masonry: 15,000  m3
Prefabricated buildings: 5,000  m2

Technical descriptions of the project

Construction of refinery with capacity of 120,000 barrels of gas distastes
 

Project goals:

  • Preventing raw sales, creating added value, job creation and maximized production of South Pars Gas
 
post

Construction and installation operations of the new Khoramdasht detergent factory

Construction and installation operations of the new Khoramdasht detergent factory

Construction and civil operations and electrical and mechanical installations of the northern and middle sectors of the construction project of the new detergent factory in Khoramdasht Industrial City- Takestan- Qazvin in May 2020, assigned to Parhoon Tarh Company by Pakan Beh Shoo Company via tender.


Current status of the project: Under construction

Key information of the project:

Role of Parhoon Tarh: Main contractor
Employer: Pakan Beh Shoo Company
Consultant: Zharf Andishan Consultant Engineers Company
Location: Khoramdasht Industrial City- Qazvin
Value of the project: 1,260 billion Rials
Length of the projects: 11 months

 

Project images

Volumes of the projects:

Concrete pouring: 16,000  m3
Armature: 1,000 tons
Concrete molds: 12,000  m2
Steel deck: 88 tons
Ceramic tiles: 22,000  m2
Sandwich panels: 48,000  m2

Technical descriptions of the project:

Production and liquid packaging building: 22,000  m2
Gel pod production and packaging building: 830  m2
Industrial liquids production and packaging building: 600  m2
Toothpaste production and packaging building: 2,400  m2
Sulfonation building: 4,700  m2
Product warehouse: 16,000  m2
Passage and power posts: 450  m2
Engine room: 1,100  m2
 

 

Goals of the project:

  • Construction of a detergent factory with annual capacity of 420,000 tons, including laundry detergents, dishwashing liquids, toothpaste, glass cleaner etc.
 

Astara Grain Terminal Construction

Astara Grain Terminal Construction

Construction and civil operations and installations of the Astara Grain Terminal in April 2019, from Astara Ghaleh Azari Company to Parhoon Tarh Company.

Astara Grain Terminal is being constructed with capacity of 30,000 tons at the primary phase and 30,000 tons in the second expansion phase, located at the Astara Customs Grand Complex with investments from I.R.I. Railways and private foreign investment (Russian-Azerbaijani firm).

Construction of all administrative, storage, station, loading and unloading, firefighting, respective concrete reservoir, trans and laboratory buildings, installation of 470 units of 25 meter candles, concrete foundation for silos, landscaping and greenery and among the executive operations of the project.


Current status of the project: Completed

Key information of the project:

Contractor: Collaboration between Parhoon Tarh- Tana Energy as chief contractor
Employer: Astara Ghaleh Azari Company
Consultant: Pasilo Consultant Engineers from Iran- INNOPRO Consultation from Azerbaijan
Location of the project: Mazandaran Province- City of Astara
Value of the contract: 3 million euros
Length of the contract: 31 months

 

Project images

Major volumes of the project:

Overall volume of concrete pouring: 20,000 cubic meters
Overall volume of soil works: 65,000 cubic meters
Armatures: 1,900
Concrete candles: 470 units with depth of 25 meters

 

Goals of the project:

  • Astara Grain Terminal was constructed based on the domestic need for increase of commerce and establishment of depots for imported grains at border regions.
 
post

Caspian Pipe Plant Complex

Caspian Pipe Plant Complex

Industrial manufacturing company Caspian Pipe Plant Complex with industry trends polyethylene water pipe From size 16 to 630 mm and pipe production of gas from size 25 to 225 mm.Caspian pipe Tabaerstan Co, an industrial manufacturer and a leader in Polyethylene production in the country takes pride for its decade of activity to benefit from expert knowledge of engineers , personnel and international technologies to produce Polyethylene water and gas pipes, thus to be a part of glorious and mighty Iranian industry.Our reputable company is actively involved in production of specialized Polyethylene pipes under commercial name of Caspian Pipe in Industrial city of Jouybar in Mazandaran state.

Status of Project: In Progress

Project Highlights

Role of Parhoon Tarh: Contractor for complete execution of executive activities Client:Personal investor Location: Mazandaran Province Equipment Cost:300 billion Rials Project Cost:1 million euros Project Duration: 18 Months

 

Featured Images

Project Volumes

Concrete Work: 850  m3 Excavation: 717  m3 Formwork: 1,526  m2 Reinforcement: 57 T Sandwich Panel: 8,670  m2 Steel Structures: 653 T

Project Goals

  • industry trends polyethylene water pipe From size 16 to 630 mm and pipe production of gas from size 25 to 225 mm

Project Stakeholders

Isfahans Refinery

Utility and offsite units of isfahans refinery industrial buildings

Isfahan refinery has developed and upgraded the refinery in order to reduce the con­ sumption of refineries, increase gasoline and improve its quality to acceptable levels. The refinery promotion plan should look at the energy and environmental protection (environmental plan) and the reduction of production costs. We are constructing civil and piping parts of utility and offsite units in the project.


Status of Project: Completed

Project Highlights

Role of Parhoon Tarh: Contractor
Client: Oil Design & Construction Co. (ODCC)
Location: Iran-Isfahan Province
Project Cost(along with purchase & installation of cranes): 9.5 million USD
Project Duration: 7 Months

 

Featured Images

Project Volumes

Concrete Work: 30000 m3
Excavation: 180000 m3
Formwork: 30000 m2
Reinforcement: 3000000 Kg
GRV/GRE/GRP Piping Volume: 53,000 Dia-lnch

Project Specification

Civil and piping parts

of utility and offsite units

Project Goals

  • Reduce the consumption of refineries.
  • Increase gasoline and improve its quality to acceptable levels.

Project Stakeholders

post

South Pars 13th Phase Laydown Roofed Warehouse & Landscaping

South Pars 13th Phase Laydown Roofed Warehouse & Landscaping

Construction of these warehouses was started with the objectives of storing equipment’s and materials close to the execution sites. Parhoon Tarh Co. was responsible for construction of all civil, architectural, electrical and mechanical works except steel structures.


Status of Project: Completed

Project Highlights

Role of Parhoon Tarh: Main Contractor
Client: P.P.I (Petro Paidar Iranian) Co.
Consultant Engineer: P.P.I (Petro Paidar Iranian) Co.
Location: Iran-Bushehr Province
Project Cost: 5 million USD
Project Duration: 8 months

 

Featured Images

Project Volumes

Concrete Volume: 5,500 m3
Sandwich Panel: 25,000 m2

Project Specification

Number of Warehouses: 12,000 m2
Total Area: 18,000 m2
Height: 9 m

Project Goals

  • Provision of required warehouses for equipment’s and materials used in 13th phase of South Pars

Project Stakeholders

post

Erection of Equipment For MEG Unit

Erection of Equipment For MEG Unit

M.E.G Mono ethylene project as one of the (main) plans of Jam petrochemical complex is located in Assaluyeh. Basic engineering & designing of this project was executed by Takni Mont Company, while final design and procurement was completed by Pidec-Takni Mont J.V. Erection of mechanical equipment’s of this complex was awarded to Naft Gostare Gheshm Co. as main contractor. Parhoon Tarh Co. as full authorized representative of main contractor was responsible for managing of execution process.


Status of Project: Completed

Project Highlights

Role of Parhoon Tarh: Construction Manager (CM)
Owner: Naft Gostare Gheshm (Main contractor as client)
Client: National Petrochemical Industries co.
Location: Iran-Bushehr province
Project Cost: 15 millions USD (Main contract) 1 million USD (Parhoon Tarh portion)
Project Duration: 14 months

 

Featured Images

Project Volumes

Equipments & Materials: 15,800 tons
Steel Structures: 2,000 tons
Above Ground Piping: 200,000 dia-inches
Electrical Cabling: 241 km
I&C Cabling: 181.5 km
Painting: 72,295 m2

Project Goals

  • Directing floods
  • Annual production of 400,000 tons of mono ethylene

Project Stakeholders

post

Ilam Cement Extension Project

Ilam Cement Extension Project

Located in 15 km from Sar Abeleh city, construction of concrete silos of Ilam cement production line was managed by Parhoon Tarh Co. Due to the fact that progress of the project was limited because of various prevailing social conditions, thorough an agreement with the National Construction Company (Main Contractor), Parhoon Tarh Co. was appointed as construction management of 5 silos including clinker, raw material, and bypass silos. Fortunately civil works of all 5 silos have been managed in 7 months with great quality.


Status of Project: Completed

Project Highlights

Role of Parhoon Tarh: Construction Manager (CM)
Client: Ilam cement company (Owner) National Construction Company (Main contractor as client)
Consultant Engineer: Sazeh Andishan Consulting Engineers
Location: Iran-Ilam Province
Project Cost: 16 millions USD (Main contract) 1 million USD (Parhoon Tarh portion)
Project Duration: 24 months

 

Featured Images

Project Volumes

Concrete Volume: 52,000 m3
Formwork: 94,000 m2
Reinforcement: 7,000 tons
Steel Works: 3,100 tons
Excavation: 190,000 m3

Project Specification

Number of Silos: 5 Units

Project Goals

  • Providing the sufficient spaces for storing of cement

Project Stakeholders

post

Construction & Civil Works of Light Polyethylene Plant Structures and Facilities

Construction & Civil Works of Light Polyethylene Plant Structures and Facilities

A unit of “Tenth Olefin”, Assaluyeh Linear low-density polyethylene (L.L.D.P.E) is situated in Assaluyeh port, Jam petrochemical. This unit presents capacity of 300,000 tons for Polymeric materials production. Parhoon Tarh Co. was responsible for managing of this contract as the project manager and also full authorized representative of client.


Status of Project: Completed

Project Highlights

Role of Parhoon Tarh: Construction Manager (CM)
Owner: Jam PCC
Client: Naft Gostar Gheshm Co.
Location: Iran-Bushehr province
Project Cost: 15 million USD (Main Contract), 1 million USD (Parhoon Tarh Portion)
Project Duration: 30 months

 

Featured Images

Project Volumes

Concrete Volume: 31,000 m3
Formwork: 64,000 m2
Reinforcement: 3,250 tons
Piping: 19,000 m
Base and Sub Base Material: 12,000 m3
HVAC Equipment: 10 units

Project Goals

  • Assaluyeh light linear Polyethylene plant is one of the ten largest Olefin plants in the world which produces 300,000 tons of polymers per annum

Project Stakeholders