Isfahans Refinery

Utility and offsite units of isfahans refinery industrial buildings

Isfahan refinery has developed and upgraded the refinery in order to reduce the con­ sumption of refineries, increase gasoline and improve its quality to acceptable levels. The refinery promotion plan should look at the energy and environmental protection (environmental plan) and the reduction of production costs. We are constructing civil and piping parts of utility and offsite units in the project.


Status of Project: In Progress

Project Highlights

Role of Parhoon Tarh: Contractor
Client: Oil Design & Construction Co. (ODCC)
Location: Iran-Isfahan Province
Project Cost(along with purchase & installation of cranes): 9.5 million USD
Project Duration: 7 Months

 

Featured Images

Project Volumes

Concrete Work: 30000 m3
Excavation: 180000 m3
Formwork: 30000 m2
Reinforcement: 3000000 Kg
GRV/GRE/GRP Piping Volume: 53,000 lnch-Dia

Project Specification

Civil and piping parts

of utility and offsite units

Project Goals

  • Reduce the consumption of refineries.
  • Increase gasoline and improve its quality to acceptable levels.

Project Stakeholders

post

South Pars 13th Phase Laydown Roofed Warehouse & Landscaping

South Pars 13th Phase Laydown Roofed Warehouse & Landscaping

Construction of these warehouses was started with the objectives of storing equipment’s and materials close to the execution sites. Parhoon Tarh Co. was responsible for construction of all civil, architectural, electrical and mechanical works except steel structures.


Status of Project: Completed

Project Highlights

Role of Parhoon Tarh: Main Contractor
Client: P.P.I (Petro Paidar Iranian) Co.
Consultant Engineer: P.P.I (Petro Paidar Iranian) Co.
Location: Iran-Bushehr Province
Project Cost: 5 million USD
Project Duration: 8 months

 

Featured Images

Project Volumes

Concrete Volume: 5,500 m3
Sandwich Panel: 25,000 m2

Project Specification

Number of Warehouses: 12,000 m2
Total Area: 18,000 m2
Height: 9 m

Project Goals

  • Provision of required warehouses for equipment’s and materials used in 13th phase of South Pars

Project Stakeholders

post

Erection of Equipment For MEG Unit

Erection of Equipment For MEG Unit

M.E.G Mono ethylene project as one of the (main) plans of Jam petrochemical complex is located in Assaluyeh. Basic engineering & designing of this project was executed by Takni Mont Company, while final design and procurement was completed by Pidec-Takni Mont J.V. Erection of mechanical equipment’s of this complex was awarded to Naft Gostare Gheshm Co. as main contractor. Parhoon Tarh Co. as full authorized representative of main contractor was responsible for managing of execution process.


Status of Project: Completed

Project Highlights

Role of Parhoon Tarh: Construction Manager (CM)
Owner: Naft Gostare Gheshm (Main contractor as client)
Client: National Petrochemical Industries co.
Location: Iran-Bushehr province
Project Cost: 15 millions USD (Main contract) 1 million USD (Parhoon Tarh portion)
Project Duration: 14 months

 

Featured Images

Project Volumes

Equipments & Materials: 15,800 tons
Steel Structures: 2,000 tons
Above Ground Piping: 200,000 dia-inches
Electrical Cabling: 241 km
I&C Cabling: 181.5 km
Painting: 72,295 m2

Project Goals

  • Directing floods
  • Annual production of 400,000 tons of mono ethylene

Project Stakeholders

post

Ilam Cement Extension Project

Ilam Cement Extension Project

Located in 15 km from Sar Abeleh city, construction of concrete silos of Ilam cement production line was managed by Parhoon Tarh Co. Due to the fact that progress of the project was limited because of various prevailing social conditions, thorough an agreement with the National Construction Company (Main Contractor), Parhoon Tarh Co. was appointed as construction management of 5 silos including clinker, raw material, and bypass silos. Fortunately civil works of all 5 silos have been managed in 7 months with great quality.


Status of Project: Completed

Project Highlights

Role of Parhoon Tarh: Construction Manager (CM)
Client: Ilam cement company (Owner) National Construction Company (Main contractor as client)
Consultant Engineer: Sazeh Andishan Consulting Engineers
Location: Iran-Ilam Province
Project Cost: 16 millions USD (Main contract) 1 million USD (Parhoon Tarh portion)
Project Duration: 24 months

 

Featured Images

Project Volumes

Concrete Volume: 52,000 m3
Formwork: 94,000 m2
Reinforcement: 7,000 tons
Steel Works: 3,100 tons
Excavation: 190,000 m3

Project Specification

Number of Silos: 5 Units

Project Goals

  • Providing the sufficient spaces for storing of cement

Project Stakeholders

post

Construction & Civil Works of Light Polyethylene Plant Structures and Facilities

Construction & Civil Works of Light Polyethylene Plant Structures and Facilities

A unit of “Tenth Olefin”, Assaluyeh Linear low-density polyethylene (L.L.D.P.E) is situated in Assaluyeh port, Jam petrochemical. This unit presents capacity of 300,000 tons for Polymeric materials production. Parhoon Tarh Co. was responsible for managing of this contract as the project manager and also full authorized representative of client.


Status of Project: Completed

Project Highlights

Role of Parhoon Tarh: Construction Manager (CM)
Owner: Jam PCC
Client: Naft Gostar Gheshm Co.
Location: Iran-Bushehr province
Project Cost: 15 million USD (Main Contract), 1 million USD (Parhoon Tarh Portion)
Project Duration: 30 months

 

Featured Images

Project Volumes

Concrete Volume: 31,000 m3
Formwork: 64,000 m2
Reinforcement: 3,250 tons
Piping: 19,000 m
Base and Sub Base Material: 12,000 m3
HVAC Equipment: 10 units

Project Goals

  • Assaluyeh light linear Polyethylene plant is one of the ten largest Olefin plants in the world which produces 300,000 tons of polymers per annum

Project Stakeholders

post

Civil Works for Roadways of the 1st Phase of PCC

Civil Works for Roadways of the 1st Phase of PCC

This project is of great importance to define. The main features of the project consist of: directing floods, routing and locating main feed pipes of petrochemical units, providing access roads and entrances for various Petrochemical Units, as well as execution of heavy concrete structures including bridges, water ways, and retaining walls along with the subsidiary activities such as large excavations and associated minor parts. On the grounds that Tablieh Co., main contractor, had been aware of Parhoon Tarh Co.’s strengths, they introduced one of the board members of Parhoon Tarh Co. as full authorized representative. Fortunately, Parhoon Tarh Co. had a great performance in this project in that could achieve employers’ satisfaction. Consequently, Tablieh Co. stated that “despite the complexity and the special status of this project, structures distribution, frequent changes of plans, and lack of traffic restrictions in Assaluyeh operations, Parhoon Tarh Co. not only successfully accomplish all civil works, but also go well beyond the expected content of agreement.


Status of Project: Completed

Project Highlights

Role of Parhoon Tarh: Construction Manager (CM)
Owner: National Petrochemical Industries Company
Client: Tablieh Co.
Location: Iran-Bushehr Province
Project Cost: 15 million USD (Main Contract) , 1 million USD (Parhoon Tarh Portion)
Project Duration: 32 months

 

Featured Images

Project Volumes

Concrete Volume: 60,000 m3
Formwork: 100,000 m2
Reinforcement: 7,000 tons
Earth Works: 700,000 m3

Project Goals

  • Directing floods
  • Routing and locating the main feed pipes
  • Provision of access roads and entrances

Project Stakeholders

post

South Pars 13th Phase Underground & Piping Works

South Pars 13th Phase Underground & Piping Works

This project is defined as Utility Units of 13th phase of the “Southern Pars development plan”. Parhoon Tarh is responsible for execution of all civil works and installation of underground piping system. This project in addition to construction of industrial buildings, camps and warehouses of 13th phase has presented this company as an influential firm in Southern Pars.


Status of Project: In Progress

Project Highlights

Role of Parhoon Tarh: Main Contractor
Client: Neyrperse Co. (Mapna Group)
Consultant Engineer: Neyrperse Co. (Mapna Group)
Location: Iran-Bushehr Province
Project Cost: 13 million USD
Project Duration: 10 months

 

Featured Images

Project Volumes

Excavation: 31,000 m3
Concrete Volume: 14,500 m3
Formwork: 14,000 m2
Reinforcement: 1,470 tons
Piping: 21,000 m

Project Specification

Number of Units: 16

Project Goals

  • Developing of 13th phase of South Pars plan
  • Extension of underground civil works of utility units

Project Stakeholders

post

South Pars 13th Phase Camp Structures and Landscaping

South Pars 13th Phase Camp Structures and Landscaping

In order to provide living accommodation and required facilities for human resources in 13th phase of South Pars, the owner assigned the construction of camps to Parhoon Tarh Company. This project includes construction of engineering, management, administration, family dormitories and guard houses.


Status of Project: Completed

Project Highlights

Role of Parhoon Tarh: Main Contractor
Client: P.P.I (Petro Paidar Iranian) Co.
Consultant Engineer: P.P.I (Petro Paidar Iranian) Co.
Location: Iran-Bushehr Province
Project Cost: 6 million USD
Project Duration: 7 months

 

Featured Images

Project Volumes

Concrete Volume: 3,000 m3
Steel Works: 130 tons
Sandwich Panel: 40,000 m2
Doors & Windows: 2,100 m2

Project Specification

Camp Structures Area: 12,000 m2
Types of Camps: In 7 types
Number of Camps: 50 units
Landscaping Area: 25,000 m2

Project Goals

  • Provision of living accommodation for human resources

Project Stakeholders

post

Civil Works For Navard Varagh Ahvaz

Civil Works For Navard Varagh Ahvaz

Ahvaz Navard Varagh project as an industrial project is located in 10th kilometer of Ahvaz-Bandere Imam Khomeini road. Construction of 4th part of foundations as well as execution of required concrete structures for machinery and equipment’s of the project was awarded to this company as the winner of a tender. All mentioned scopes of works as responsibilities of Parhoon Tarh Co. totally completed in May 2008.


Status of Project: Completed

Project Highlights

Role of Parhoon Tarh: Main Contractor
Client: Khuzestan Foolad Oxin Co.
Consultant Engineer: Fanavar Sanat Madan Consulting Engineers
Location: Iran-Khuzestan Province
Project Cost: 4 million USD
Project Duration: 10 months

 

Featured Images

Project Volumes

Concrete Volume: 12,000 m3
Formwork: 17,000 m2
Reinforcement: 1,200 tons
Steel Works: 90 tons

Project Specification

Total Area: 9,000 m2

Project Goals

  • Construction of required concrete & steel structures for machinery & equipment’s

Project Stakeholders

post

South Pars 13th Phase Industrial Buildings

South Pars 13th Phase Industrial Buildings

13th phase of South Pars with objective of gas extraction for about 2 billion cubic foot is considered as a natural gas condensate field which is located in the Persian Gulf. This project includes design control, material procurement, and construction of decentralized industrial buildings. Moreover, installation of all related equipment’s is another responsibility of this company.


Status of Project: Completed

Project Highlights

Role of Parhoon Tarh: Main Contractor
Client: P.P.I (Petro Paidar Iranian) Co.
Consultant Engineer: P.P.I (Petro Paidar Iranian) Co.
Location: Iran-Bushehr Province
Project Cost: 23 million USD
Project Duration: 18 months

 

Featured Images

Project Volumes

Concrete Volume: 37,000 m3
Formwork: 120,000 m2
Reinforcement: 4,500 tons
Earth Works: 52,000 m3

Project Specification

Industrial Buildings: 30,000 m2 including 10 substations, 1 firefighting, 1 switchgear room, and 1 view gallery

Project Goals

  • Provision of demanded power for different units of south Pars refinery
  • Controlling & processing of existing units in the refinery

Project Stakeholders