National Customs Academy of Kabul


Gallery Pictures

National Customs Academy of KabulNational Customs Academy of KabulNational Customs Academy of KabulNational Customs Academy of KabulNational Customs Academy of KabulNational Customs Academy of KabulNational Customs Academy of KabulNational Customs Academy of Kabul

Project Highlights

Role of Parhoon Tarh: Main Contractor
Client: The European Union.
Consultant Engineer: Sim S.pA Co.
Location: Kabul, Afghanistan
Project Cost: 3 Million Euro
Project Duration: 18 months

Project Volumes

Excavation: 7,000 square feet
Concrete works: 2,000 square feet
Frame working: 11,000 square feet
Steel Works: 3 tons
Reinforcement: 110 tons
Landscaping: 8,000 square feet

Project Specification

Total area of administrative buildings: 600 m2
Total area of didactic buildings: 1600 m2
Type of Structure: Concrete structure

Project Goals

Organization and training of Customs Service personnel in Afghanistan.