Ilam Cement Extension Project


Gallery Pictures

Ilam Cement Extension Project

Project Highlights

Role of Parhoon Tarh: Construction Manager (CM)
Client: Ilam cement company (Owner) National Construction Company (Main contractor as client)
Consultant Engineer: Sazeh Andishan Consulting Engineers
Location: Iran-Ilam Province
Project Cost: 16 millions USD (Main contract) 1 million USD (Parhoon Tarh portion)
Project Duration: 24 months

Project Volumes

Concrete Volume: 52,000 m3
Formworks: 94,000 m2
Reinforcement: 7,000 tons
Steel Works: 3,100 tons
Excavation: 190,000 m3

Project Specification

Number of silos: 5 Units

Project Goals

Providing the sufficient spaces for storing of cement