South Pars 13th Phase Camp Structures and Landscaping


Gallery Pictures

South Pars 13th Phase Camp Structures and LandscapingSouth Pars 13th Phase Camp Structures and LandscapingSouth Pars 13th Phase Camp Structures and LandscapingSouth Pars 13th Phase Camp Structures and LandscapingSouth Pars 13th Phase Camp Structures and LandscapingSouth Pars 13th Phase Camp Structures and LandscapingSouth Pars 13th Phase Camp Structures and LandscapingSouth Pars 13th Phase Camp Structures and LandscapingSouth Pars 13th Phase Camp Structures and Landscaping

Project Highlights

Role of Parhoon Tarh: Main Contractor
Client: P.P.I (Petro Paidar Iranian) Co.
Consultant Engineer: P.P.I (Petro Paidar Iranian) Co.
Location: Iran-Bushehr Province
Project Cost: 6 million USD
Project Duration: 7 months

Project Volumes

Sandwich Panel: 40,000 m2
Concrete Volume: 3,000 m3
Steel Works: 130 tons
Doors & Windows: 2,100 m2

Project Specification

Camp structures area: 12,000 m2
Types of camps: In 7 types
Number of camps: 50 units
Landscaping area: 25,000 m2

Project Goals

Provision of living accommodation for human resources.