Rudeshur Simple Cycle


Gallery Pictures

Rudeshur Simple CycleRudeshur Simple CycleRudeshur Simple CycleRudeshur Simple CycleRudeshur Simple CycleRudeshur Simple CycleRudeshur Simple CycleRudeshur Simple CycleRudeshur Simple Cycle

Project Highlights

Role of Parhoon Tarh: Managing Contractor (MC)
Client: Arian Mahtab Gostar Co.
Consultant Engineer: Electrowatt Consulting Engineers as Designer & Vala Energy Co. as supervisor
Location: Iran-Markazi Province
Project Cost: 208 million Euros (Main Contract) - 1 million USD (Parhoon Tarh Portion)
Project Duration: 30 months

Project Volumes

Capacity of 1st phase: 789 MW
Capacity of all phases: 2100 MW
Type of GTG units: Siemens V 94.3.2a
Number of units: 3 × 262.9 MW (1st Phase)

Project Goals

Considering annual growth of the national demand as well as the I.R.I policies to activate the private sector in supplying electricity
Rudeshur SCPP with a final capacity of 2,100 MW by 8 units completed by the private sector in an aim to make up the part of the national grid demand.