Sanandaj Combined Cycle


Gallery Pictures

Sanandaj Combined Cycle Sanandaj Combined Cycle Sanandaj Combined Cycle Sanandaj Combined Cycle Sanandaj Combined Cycle Sanandaj Combined Cycle Sanandaj Combined Cycle

Project Highlights

Role of Parhoon Tarh: Main Contractor
Client: MAPNA Group
Consultant Engineer: Moshanir Co. as the Consulting Engineers & Ghods Niroo Co. as the supervisor
Location: Iran-Kurdistan Province
Project Cost: 20 million USD
Project Duration: 22 months

Project Volumes

Concrete Volume: 15,000 m3
Formwork: 34,000 m2
Reinforcement: 1,500 tons
Steel Structures: 2,150 tons
Sandwich Panel: 10,000 m2

Project Specification

Capacity: 960 MW
Number of units: 4 gas units & 2 steam units
Capacity of each unit: 160 MW
Gas Turbines: Tuga V94.2

Project Goals

Power generation for supporting other cities