Seymareh Hydroelectric Plant


Gallery Pictures

Seymareh Hydroelectric PlantSeymareh Hydroelectric PlantSeymareh Hydroelectric PlantSeymareh Hydroelectric PlantSeymareh Hydroelectric PlantSeymareh Hydroelectric PlantSeymareh Hydroelectric PlantSeymareh Hydroelectric PlantSeymareh Hydroelectric Plant

Project Highlights

Role of Parhoon Tarh: EPC Contractor as member of Tablieh-Parhoon Tarh J.V.
Client: Iran Power and Water Development Company
Consultant Engineer: Mahab Ghods Consulting Engineers
Location: Iran-Ilam Province
Project Cost: 42 million USD
Project Duration: 103 months

Project Volumes

Open air Excavation: 60,000 m3
Concrete Volume: 70,000 m3
Reinforcement: 3,500 tons
Formwork: 48,000 m2

Project Specification

Power house type: Surface
Power house dimensions: L= 97.70 m, W= 51.65 m, H= 57.15 m
Number of units: 3 vertical axes 160 MW Francis units

Project Goals

Production of 850 G WHr hydroelectric energy annually
Control of seymareh river flood
Regulating water flow to Karkheh dam
Supply of regional downstream water requirements