West Mazandaran Combined Cycles Power Plant


Gallery Pictures

West Mazandaran Combined Cycles Power PlantWest Mazandaran Combined Cycles Power Plant

Project Highlights

Role of Parhoon Tarh: Contractor for complete execution of executive activities
Client: Caspian Mahtab Power Generation Co.
Consultant Engineer: Raz Ahang Co.
Location: Mazandaran Province
Project Cost(along with purchase & installation of cranes): 612,979,161,533
Project Duration: 30 Months

Project Volumes

Concrete work: 22507 m3
Excavation: 161148 m3
Form Work: 45104 m2
Armature Work: 28155575 Kg
Sandwich Panel: 19634 m2
Metal structures: 2463611 Kg

Project Specification

Type of power plant: Combined cycle
Power plant capacity: 450 MV
Number of Units: 1 Gas Unit

Project Goals

Power Generation & Improvement of Environmental Conditions