Project Highlights

Role of Parhoon Tarh: Managing Contractor (MC)
Client: MAPNA Group
Consultant Engineer: Moshanir Consulting Engineers
Location: Iran-Yazd Province
Project Cost: 18 million USD
Project Duration: 40 months

Project Volumes

Concrete Volume: 31,000 m3
Formwork: 78,000 m2
Reinforcement: 3,300 tons
Steel Works: 3,300 tons
Sandwich Panel: 20,500 m2

Project Specification

Capacity: 478 MW
Number of gas units: 2*159 MW gas units (V94.2) Number of steam units: 1*143 steam unit
Capacity of solar unit: 3,300 tons
Steel Works: 17 MW

Project Goals

Developing and using clean energy, and making optimum use of the solar energy