Project Highlights

Role of Parhoon Tarh: Contractor
Client: Farab Company
Consultant Engineer: Amberg Engineers
Location: Sri Lanka
Project Cost: 35.5 million USD
Project Duration: 25 Months

Project Volumes

Concrete Volume: 1,000 m3
Excavation: 222,000 m3

Project Specification

Length of tunnel: 15 km
Tunnel outer diameter: 4.3 m
Tunnel inner diameter: 3.8 m

Project Goals

Construction of Headrace Tunnel -15 Km Length- of the Uma Oya Multipurpose Development Project in Sri Lanka by mechanized method