Project Highlights

Role of Parhoon Tarh: Contractor
Client: Farab Company
Consultant Engineer: Mahab Ghodds Consultant
Location: Sri Lanka
Project Cost: 6.3 million USD
Project Duration: 215 Days

Project Volumes

Concrete Volume: 2,000 m3
Reinforcement & Steel Works: 40 tons
Formwork: 500 m2
Excavation: 24,500 m3

Project Specification

Length of tunnel: 750 m
VCA Tunnel diameter: 2.55 m
LHT Tunnel diameter: 2.15 m
LC Tunnel diameter: 2.15 m

Project Goals

Construction of some spaces for installations and fittings in order to transfer water from Headrace Tunnel to Powerplant