The contract of Almaar dam and irrigation network designing was signed in 2012 between Tedis company of Tajikistan (main contractor) and Arian Parhoon. Almaar project is 34 kilometers far Maimana city, Faryab province, Afghanistan. The project includes a 68-meter-high concrete gravity dam and irrigation network in an area of 4000 hectares.


Status of Project: Completed

Project Highlights

Role of Parhoon Tarh: Main Contractor
Owner: Ministry of Water and Power in the Islamic Republic of Afghanistan
Client: Tedis (Tajikistan)
Location: Afghanistan, Faryab, Maimana
Project Cost: 1.55 million USD
Project Duration: 22 Months

 

Featured Images

Project Specification

Type of Dam: Gravity Dam
Length at the Crown: 350 m
Spillway: Free Spillway at the Crown
Drainage Network: 3995 Hectares

Project Goals

  • Providing water for downstream lands