Abadan Gas Power Plant
Abadan refinery third power plant project, having installed capacity of 210 MW power generations, was completed by Parhoon Tarh Company. This company was responsible for execution of all related civil works of the project which was awarded by Farab co. as the client.
Status of Project: Completed
Project Highlights
Role of Parhoon Tarh: Main Contractor
Client: Farab Co.
Consultant Engineer: Mesinan Consulting Engineers
Location: Iran-Khuzestan Province
Project Cost: 20 million USD
Project Duration: 41 months

Featured Images
Project Volumes
Concrete Volume: 17,000 m3
Formwork: 32,000 m3
Reinforcement: 1,900 tons
Steel Structures: 3,200 tons
Sandwich Panel: 12,000 m2
Project Specification
Capacity: 210 MW
Number of Units: 7*30 MW gas units
Project Goals
- Power production
- Replacing old generators of Abadan refinery
- Stability of oil production