Sanandaj Cooling Towers

Because of Parhoon Tarh Co’s great performance in execution of Sanandaj combined cycle power plant and gaining employer’s satisfaction, the client decided to extend Parhoon Tarh’s responsibility by assigning the construction of two cooling towers. All civil works of the mentioned cooling towers with maximum height of 125 m were completed by this company implementing of climbing form working system.


Status of Project: Completed

Project Highlights

Role of Parhoon Tarh: Main Contractor
Client: MAPNA Group
Consultant Engineer: Moshanir Co. as Consulting Engineers & Ghods Niroo Co. as the supervisor
Location: Iran-Kurdistan Province
Project Cost: 15 million USD
Project Duration: 18 months

 

Featured Images

Project Volumes

Number of Towers: 2 units
Height from Foundation: 125 m
Maximum Diameter: 73 m
Thickness: Vary from 18 cm to 125 cm

Project Goals

  • Cooling the working fluid