Hendurabi Airport
Status of Project: Completed
Project Highlights
Role of Parhoon Tarh: Contractor
Client:Jahad Nasr company
Consultant: Emen rah company
Location: Hendurabi Island
Project Duration: 30 Months

Featured Images
Project Specification
Band: 25-07
Airport Security Fence: 90 Hectare
Band Width: 30 meters and shoulder path 5 and 7 meters.over run 90 and 60 meters in the Respectively East and West side.
Band Lenght: 1480 meters Sit up and take off the air plane ATR72 AND F50.
Taxi Way: vertical taxi way with a length of 212 meters and a width of 18 meters plus a shoulder 5 and 7 meters.
Apron: Dimensions 80 × 140 m plus 5 and 7 m shoulders with the position of 3 stations for air planes ATR72.
Helipad: 2 station locations for the chopper.
Asphalt: Pouring asphalt in the runway
Lighting:lighting the band,taxi ways and apron.
Project Goals
The construction of the airport for faster and easier transfer of domestic and foreign specialists