South Pars 13th Phase Laydown Roofed Warehouse & Landscaping

Construction of these warehouses was started with the objectives of storing equipment’s and materials close to the execution sites. Parhoon Tarh Co. was responsible for construction of all civil, architectural, electrical and mechanical works except steel structures.


Status of Project: Completed

Project Highlights

Role of Parhoon Tarh: Main Contractor
Client: P.P.I (Petro Paidar Iranian) Co.
Consultant Engineer: P.P.I (Petro Paidar Iranian) Co.
Location: Iran-Bushehr Province
Project Cost: 5 million USD
Project Duration: 8 months

 

Featured Images

Project Volumes

Concrete Volume: 5,500 m3
Sandwich Panel: 25,000 m2

Project Specification

Number of Warehouses: 12,000 m2
Total Area: 18,000 m2
Height: 9 m

Project Goals

  • Provision of required warehouses for equipment’s and materials used in 13th phase of South Pars