post

Abadan Gas Power Plant

Abadan Gas Power Plant

Abadan refinery third power plant project, having installed capacity of 210 MW power generations, was completed by Parhoon Tarh Company. This company was responsible for execution of all related civil works of the project which was awarded by Farab co. as the client.


Status of Project: Completed

Project Highlights

Role of Parhoon Tarh: Main Contractor
Client: Farab Co.
Consultant Engineer: Mesinan Consulting Engineers
Location: Iran-Khuzestan Province
Project Cost: 20 million USD
Project Duration: 41 months

 

Featured Images

Project Volumes

Concrete Volume: 17,000 m3
Formwork: 32,000 m3
Reinforcement: 1,900 tons
Steel Structures: 3,200 tons
Sandwich Panel: 12,000 m2

Project Specification

Capacity: 210 MW
Number of Units: 7*30 MW gas units

Project Goals

  • Power production
  • Replacing old generators of Abadan refinery
  • Stability of oil production

Project Stakeholders

post

Aliabad Gas Power Plant

Aliabad Gas Power Plant

Aliabad Gas Power Plant is located in Golestan province in Iran. Execution of all civil works of this power plant was awarded to Parhoon Tarh Company due to its brilliant experience specially in construction of power plants.


Status of Project: Completed

Project Highlights

Role of Parhoon Tarh: Main Contractor
Client: MAPNA Group
Consultant Engineer: Ghods Niroo Consulting Engineers
Location: Iran-Golestan Province
Project Cost: 25 million USD
Project Duration: 22 months

 

Featured Images

Project Volumes

Concrete Volume: 54,000 m3
Formwork: 100,000 m3
Reinforcement: 3,500 tons
Steel Works: 4,000 tons
Sandwich Panel: 20,000 m2

Project Specification

Capacity: 1000 MW
Number of Units: 6*162 gas units

Project Goals

  • Power production of 1000 MW by 6*162 MW units

Project Stakeholders

post

Erection of Equipment For MEG Unit

Erection of Equipment For MEG Unit

M.E.G Mono ethylene project as one of the (main) plans of Jam petrochemical complex is located in Assaluyeh. Basic engineering & designing of this project was executed by Takni Mont Company, while final design and procurement was completed by Pidec-Takni Mont J.V. Erection of mechanical equipment’s of this complex was awarded to Naft Gostare Gheshm Co. as main contractor. Parhoon Tarh Co. as full authorized representative of main contractor was responsible for managing of execution process.


Status of Project: Completed

Project Highlights

Role of Parhoon Tarh: Construction Manager (CM)
Owner: Naft Gostare Gheshm (Main contractor as client)
Client: National Petrochemical Industries co.
Location: Iran-Bushehr province
Project Cost: 15 millions USD (Main contract) 1 million USD (Parhoon Tarh portion)
Project Duration: 14 months

 

Featured Images

Project Volumes

Equipments & Materials: 15,800 tons
Steel Structures: 2,000 tons
Above Ground Piping: 200,000 dia-inches
Electrical Cabling: 241 km
I&C Cabling: 181.5 km
Painting: 72,295 m2

Project Goals

  • Directing floods
  • Annual production of 400,000 tons of mono ethylene

Project Stakeholders

post

Ilam Cement Extension Project

Ilam Cement Extension Project

Located in 15 km from Sar Abeleh city, construction of concrete silos of Ilam cement production line was managed by Parhoon Tarh Co. Due to the fact that progress of the project was limited because of various prevailing social conditions, thorough an agreement with the National Construction Company (Main Contractor), Parhoon Tarh Co. was appointed as construction management of 5 silos including clinker, raw material, and bypass silos. Fortunately civil works of all 5 silos have been managed in 7 months with great quality.


Status of Project: Completed

Project Highlights

Role of Parhoon Tarh: Construction Manager (CM)
Client: Ilam cement company (Owner) National Construction Company (Main contractor as client)
Consultant Engineer: Sazeh Andishan Consulting Engineers
Location: Iran-Ilam Province
Project Cost: 16 millions USD (Main contract) 1 million USD (Parhoon Tarh portion)
Project Duration: 24 months

 

Featured Images

Project Volumes

Concrete Volume: 52,000 m3
Formwork: 94,000 m2
Reinforcement: 7,000 tons
Steel Works: 3,100 tons
Excavation: 190,000 m3

Project Specification

Number of Silos: 5 Units

Project Goals

  • Providing the sufficient spaces for storing of cement

Project Stakeholders

post

Construction & Civil Works of Light Polyethylene Plant Structures and Facilities

Construction & Civil Works of Light Polyethylene Plant Structures and Facilities

A unit of “Tenth Olefin”, Assaluyeh Linear low-density polyethylene (L.L.D.P.E) is situated in Assaluyeh port, Jam petrochemical. This unit presents capacity of 300,000 tons for Polymeric materials production. Parhoon Tarh Co. was responsible for managing of this contract as the project manager and also full authorized representative of client.


Status of Project: Completed

Project Highlights

Role of Parhoon Tarh: Construction Manager (CM)
Owner: Jam PCC
Client: Naft Gostar Gheshm Co.
Location: Iran-Bushehr province
Project Cost: 15 million USD (Main Contract), 1 million USD (Parhoon Tarh Portion)
Project Duration: 30 months

 

Featured Images

Project Volumes

Concrete Volume: 31,000 m3
Formwork: 64,000 m2
Reinforcement: 3,250 tons
Piping: 19,000 m
Base and Sub Base Material: 12,000 m3
HVAC Equipment: 10 units

Project Goals

  • Assaluyeh light linear Polyethylene plant is one of the ten largest Olefin plants in the world which produces 300,000 tons of polymers per annum

Project Stakeholders

post

Chamshir Diversion System

Chamshir Dam

Chamshir dam which is located in the southwest of Iran, near the Zohreh river, is being constructed to provide 1.8 billion cubic meters water in order to irrigate about 110 hectares of downstream fertile agricultural lands. Flood controlling, power generation, and water protection of Zohreh River are other purposes of this project. Parhoon Tarh Company is responsible for construction of upstream and downstream coffer dam as well as lining of diversion tunnel in this project.


Status of Project: Completed

Project Highlights

Role of Parhoon Tarh: Main Contractor
Owner: Iran Power and Water Development Company
Client: Sabir Co.
Consultant Engineer: Tehran Sahab Consulting Engineers
Location: Iran-Kohgiluyeh & Buyerahmad Province
Project Cost: 15 million USD
Project Duration: 18 Months

 

Featured Images

Project Volumes

Coffer Dams RCC Concrete: 95,000 m3
Diversion Tunnel Concrete: 45,000 m3
Reinforcement: 2,400 tons
Formwork: 53,000 m2

Project Specification

Type of Dam: RCC (Roller Compacted Concrete)
Height of Upstream Coffer Dam: 32 m
Height of Downstream Coffer Dam: 18 m
Length of Diversion Tunnel: 760 m
Diameter of Diversion Tunnel: 12 m

Project Goals

  • Diversion of the Zohreh river water route

Project Stakeholders

post

Civil Works for Roadways of the 1st Phase of PCC

Civil Works for Roadways of the 1st Phase of PCC

This project is of great importance to define. The main features of the project consist of: directing floods, routing and locating main feed pipes of petrochemical units, providing access roads and entrances for various Petrochemical Units, as well as execution of heavy concrete structures including bridges, water ways, and retaining walls along with the subsidiary activities such as large excavations and associated minor parts. On the grounds that Tablieh Co., main contractor, had been aware of Parhoon Tarh Co.’s strengths, they introduced one of the board members of Parhoon Tarh Co. as full authorized representative. Fortunately, Parhoon Tarh Co. had a great performance in this project in that could achieve employers’ satisfaction. Consequently, Tablieh Co. stated that “despite the complexity and the special status of this project, structures distribution, frequent changes of plans, and lack of traffic restrictions in Assaluyeh operations, Parhoon Tarh Co. not only successfully accomplish all civil works, but also go well beyond the expected content of agreement.


Status of Project: Completed

Project Highlights

Role of Parhoon Tarh: Construction Manager (CM)
Owner: National Petrochemical Industries Company
Client: Tablieh Co.
Location: Iran-Bushehr Province
Project Cost: 15 million USD (Main Contract) , 1 million USD (Parhoon Tarh Portion)
Project Duration: 32 months

 

Featured Images

Project Volumes

Concrete Volume: 60,000 m3
Formwork: 100,000 m2
Reinforcement: 7,000 tons
Earth Works: 700,000 m3

Project Goals

  • Directing floods
  • Routing and locating the main feed pipes
  • Provision of access roads and entrances

Project Stakeholders

post

Dam 1 & 2 Akhtar Site Flood Control System

Dam 1 & 2 Akhtar Site Flood Control System

Considering the torrential rains and occurrence of flood in Pars area and for purpose of detention and controlling the process of flood by dam construction and water reservation behind the constructed dams and gradual discharging thereof, the executive operations of dam 1 & 2 of Akhtar Site flood control system is under construction at Kangan city, Bushehr province. This project consists of the detention gravel dam with concrete coating and execution of all hydraulic details, miscellaneous works, mobilization and demobilization of the workshop according to the map & technical specifications Almaar project is 34 kilometers far Maimana city, Faryab province, Afghanistan. The project includes a 68-meter-high concrete gravity dam and irrigation network in an area of 4000 hectares.


Status of Project: Completed

Project Highlights

Role of Parhoon Tarh: Main contractor, member of Tablieh-Parhoon Tarh joint venture
Owner: Pars Oil & Gas Company
Location: Bushehr Province
Project Cost: 730 billion rials
Project Duration: 24 Months

 

Featured Images

Project Volumes

Excavation & Rock Removal: 204,600 m3
Embankment (main frame execution): 897,600 m3

Project Specification

Type of Dam: Gravel (rock fill) with Concrete Coating (CFRD)
Length of the Dam Crown D1: 231 m
Length of the Dam Crown D2: 172.4 m
Dam Height D1: 22 m
Dam Height D2: 50 m

Project Goals

  • Protection of the downstream facilities of South Pars Phases 13, 22, & 24, against the destructive floods

Project Stakeholders

post

South Pars 13th Phase Underground & Piping Works

South Pars 13th Phase Underground & Piping Works

This project is defined as Utility Units of 13th phase of the “Southern Pars development plan”. Parhoon Tarh is responsible for execution of all civil works and installation of underground piping system. This project in addition to construction of industrial buildings, camps and warehouses of 13th phase has presented this company as an influential firm in Southern Pars.


Status of Project: Completed

Project Highlights

Role of Parhoon Tarh: Main Contractor
Client: Neyrperse Co. (Mapna Group)
Consultant Engineer: Neyrperse Co. (Mapna Group)
Location: Iran-Bushehr Province
Project Cost: 13 million USD
Project Duration: 10 months

 

Featured Images

Project Volumes

Excavation: 31,000 m3
Concrete Volume: 14,500 m3
Formwork: 14,000 m2
Reinforcement: 1,470 tons
Piping: 21,000 m

Project Specification

Number of Units: 16

Project Goals

  • Developing of 13th phase of South Pars plan
  • Extension of underground civil works of utility units

Project Stakeholders

post

South Pars 13th Phase Camp Structures and Landscaping

South Pars 13th Phase Camp Structures and Landscaping

In order to provide living accommodation and required facilities for human resources in 13th phase of South Pars, the owner assigned the construction of camps to Parhoon Tarh Company. This project includes construction of engineering, management, administration, family dormitories and guard houses.


Status of Project: Completed

Project Highlights

Role of Parhoon Tarh: Main Contractor
Client: P.P.I (Petro Paidar Iranian) Co.
Consultant Engineer: P.P.I (Petro Paidar Iranian) Co.
Location: Iran-Bushehr Province
Project Cost: 6 million USD
Project Duration: 7 months

 

Featured Images

Project Volumes

Concrete Volume: 3,000 m3
Steel Works: 130 tons
Sandwich Panel: 40,000 m2
Doors & Windows: 2,100 m2

Project Specification

Camp Structures Area: 12,000 m2
Types of Camps: In 7 types
Number of Camps: 50 units
Landscaping Area: 25,000 m2

Project Goals

  • Provision of living accommodation for human resources

Project Stakeholders